By CoolNews Investigation Team
Published: September 2025
In the heart of Nigeria’s oil-rich Niger Delta, three massive industrial complexes that were once symbols of the country’s petroleum prowess now stand as monuments to spectacular failure. The Port Harcourt, Warri, and Kaduna refineries—recipients of over $3 billion in rehabilitation funds—have become elaborate ghost towns where workers clock in with nothing to do, machines gather dust, and promises of energy independence dissolve into thin air.
This comprehensive CoolNews investigation, conducted across three states over several months, exposes the shocking reality behind one of Nigeria’s most expensive industrial scandals. Through extensive field visits, interviews with dozens of sources, and analysis of official documents, we reveal how a project meant to transform Africa’s largest oil producer into a refining powerhouse instead became a case study in systemic corruption and administrative incompetence.

The Broken Promise of Energy Independence
Nigeria’s petroleum paradox is as old as it is frustrating. Despite sitting atop some of the world’s largest oil reserves and producing over 2 million barrels daily, the country imports nearly 100% of its refined petroleum products—a dependency that costs billions annually and leaves citizens vulnerable to global fuel price shocks.
The rehabilitation of the three major refineries was supposed to end this costly irony. Launched with great fanfare and backed by massive financial commitments, the project represented more than industrial renewal—it symbolized Nigeria’s aspiration to finally harness its oil wealth for domestic prosperity.
Instead, it has become the subject of a high-profile Economic and Financial Crimes Commission (EFCC) investigation, with former Nigerian National Petroleum Company Limited (NNPCL) executives facing intense scrutiny over alleged fund mismanagement.
A History of Failed Promises.
The roots of the current crisis stretch back decades. Public records show that NNPCL has overseen multiple rehabilitation efforts since the early 2000s, each accompanied by solemn promises of operational revival that were repeatedly broken.
The pattern became depressingly familiar: grand announcements, substantial financial commitments, brief periods of activity, followed by prolonged shutdowns and excuses. Each cycle deepened public cynicism and drained the national treasury while Nigeria’s dependence on imported fuel products only intensified.
The latest rehabilitation effort, beginning in earnest around 2021, was positioned as different. The scale of investment—over $3 billion across the three facilities—was unprecedented. Officials promised this would finally break the cycle of failure and deliver energy security to Africa’s most populous nation.
As our investigation reveals, it has instead perpetuated it on a grander, more expensive scale.
Port Harcourt: The $1.5 Billion Mirage
The Facility That Time Forgot
The Port Harcourt Refining Company, sprawling across the Alesa area of Eleme Local Government in Rivers State, tells perhaps the most dramatic story of squandered opportunity. This massive complex, comprising two distinct units with a combined capacity of 210,000 barrels per day, was once the crown jewel of Nigeria’s petroleum infrastructure.
The older unit, built in 1965 with a 60,000 barrels per day capacity, represented Nigeria’s early ambitions in petroleum refining. The newer facility, constructed in 1989 with 150,000 barrels per day capacity, was meant to position the country as a regional refining hub, producing not just petrol and diesel but also kerosene and various petrochemicals.
By 2019, both units had fallen silent. Obsolescence, inadequate maintenance, and persistent vandalism of critical infrastructure had rendered the once-mighty refinery inoperable. The silence that descended over the complex was deafening—gone were the roar of machinery, the flames of furnaces, and the constant traffic of tanker trucks that had defined the facility for decades.
The $1.5 Billion Gamble
The rehabilitation plan for Port Harcourt was as ambitious as it was expensive. Divided into three carefully planned phases and budgeted at $1.5 billion, the project promised to restore the refinery to full operational capacity by 2025.
The scope was comprehensive: upgrading aging equipment, installing modern control systems, rebuilding damaged infrastructure, and implementing new safety protocols. On paper, it represented everything needed to bring a world-class refinery into the 21st century.
Former NNPCL Group Chief Executive Officer Mele Kyari became the public face of this revival. In November 2024, with considerable media fanfare, he announced that the refinery had resumed operations at 70% capacity. The projections he outlined were impressive: 1.5 million litres of diesel daily, 2.1 million litres of low-pour fuel oil, 1.4 million litres of petrol, and 900,000 litres of kerosene.
The Reality Check
CoolNews conducted multiple visits to the Port Harcourt facility between May and September 2025, each revealing the growing gap between official statements and operational reality.
Our first visit in late May coincided with NNPCL spokesman Olufemi Soneye’s announcement of a “30-day shutdown for routine maintenance.” Even then, the scope of inactivity was striking. The massive refinery complex, which should have been humming with activity, was eerily quiet.
Workers were present, but their activities were limited to administrative tasks and basic maintenance. The production units—the heart of any refining operation—showed no signs of active processing. Storage tanks that should have been cycling through constant filling and emptying appeared static.
At the adjacent Port Harcourt Refinery Depot, the situation was even more revealing. The truck park, which during operational periods would be crowded with petroleum tankers loading various products, was largely empty. Only sporadic movements of Automated Gas Oil (diesel) were observed, and these appeared to be from existing inventory rather than fresh production.
Voices from the Ground
The petroleum marketers who frequent the depot provided the most candid assessment of the situation. These men and women, whose livelihoods depend on the refinery’s output, had no incentive to misrepresent the facility’s status.
Toku, a veteran marketer who has worked the depot for over a decade, was blunt in his assessment: “Since the last time Mele Kyari came, the depot loaded only a few trucks. After that, till today, the refinery has not been working. About three months ago, from the old stock, they were loading only DPK [kerosene] and AGO [diesel], but now it’s just AGO. The refinery is not producing anything. It is not working. So, let the government stop deceiving us.”
Another marketer, who requested anonymity to avoid potential retaliation, revealed attempts to restart operations: “From what I heard, they said they planned to test-run the plant last week, but nothing happened. They said the loading bay is faulty. So here, they are only loading AGO.”
The economic impact extends beyond production issues. Independent marketers report being priced out of the limited products available: “Only major and mega companies like NNPC and Oando are lifting for now. We, the independent marketers, can’t buy from the refinery because it is too expensive. Some of us go to private depots, which are cheaper.”
The Admission of Failure
By June 2025, stakeholders were expressing public frustration. The Host Community Bulk Petroleum Retailers Association of Port Harcourt Refinery Depot issued a statement expressing “shock over the prolonged shutdown” and urging the Federal Government to “adhere to the 30-day timeline it earlier promised, warning that failure to do so would amount to taking Nigerians for granted.”
The turning point came in August 2025 when NNPCL made a startling admission. The company backtracked on its full rehabilitation claims, admitting there were “errors in the $1.5bn work” and confirming the project’s incomplete status. This acknowledgment, buried in technical language, represented a devastating admission that the massive investment had failed to achieve its primary objective.
Our most recent visit in September 2025 confirmed the continued dormancy of the facility. The refinery remained inactive, with workers engaging primarily in administrative functions while the core production infrastructure lay idle.
Warri: A Decade-Long Slumber Continues
The Delta Disappointment
The Warri Refining and Petrochemical Company, nestled in Delta State, presents perhaps the most straightforward case of rehabilitation failure. Established in 1978 with an impressive 125,000 barrels per day capacity, the facility had built a reputation not just for fuel production but also for specialized petrochemicals including polypropylene and carbon black.
The refinery’s history reflects Nigeria’s broader industrial challenges. Public records indicate it was forced to shut down in 2015 due to a combination of pipeline vandalism—a persistent problem in the Niger Delta—and cascading technical failures that made continued operation impossible.
For nearly a decade, the massive complex sat idle, its sophisticated equipment slowly deteriorating under the humid Delta climate. The shutdown had devastating effects on the surrounding community, which had grown and prospered around the refinery’s operations.
The $897.6 Million Restart
When the Federal Government approved $1.4 billion for the rehabilitation of both Warri and Kaduna refineries in 2021, Warri’s allocation of $897.6 million represented a substantial investment in the facility’s revival. The funding was meant to address not just the immediate technical issues that had forced the shutdown but also to upgrade the facility to modern standards.
The rehabilitation scope was comprehensive: replacing corroded pipelines, updating control systems, refurbishing processing units, and implementing enhanced security measures to prevent future vandalism. The project timeline projected a phased return to operations, with initial capacity targeting 60% of full capacity.
The breakthrough seemed to come on December 30, 2024, when Reuters reported the refinery’s resumption after its decade-long slumber. Mele Kyari, maintaining his role as the public champion of Nigeria’s refinery revival, declared the facility operational and projected initial operations at 60% capacity.
The Hollow Revival
CoolNews investigators visited the Warri facility in August and September 2025, finding a complex that bore little resemblance to an active refinery. The stark reality contradicted all official pronouncements of resumed operations.
The facility’s tanker park, which should serve as a bustling hub of petroleum product distribution, was completely empty during our visits. No flares were visible from the chemical processing plant—a tell-tale sign of inactive operations. Storage tanks showed no signs of the constant activity that characterizes working refineries.
Most revealing was the human element. While staff members were observed entering and leaving the complex, their activities appeared limited to routine administrative functions rather than operational management. The absence of the specialized technical teams required for refinery operations was particularly notable.
Inside Sources Reveal the Truth
Sources within the facility provided candid assessments that painted a picture of institutional dysfunction. “The WRPC staff come to work as a routine and go home at will. People are just collecting salaries, the refinery is not working,” revealed one source familiar with daily operations.
Another source, however, suggested that minimal maintenance activities were ongoing, though these appeared disconnected from any immediate operational plans. “Every NNPCL administration has its own policy. This particular administration is yet to announce its policy as regards Warri Refinery,” the source explained, highlighting the administrative uncertainty that has plagued the facility.
This policy uncertainty reflects a broader problem in Nigeria’s petroleum sector, where changes in leadership often result in completely new strategic directions, regardless of existing investments or commitments.
Kaduna: The Northern Nightmare
A Facility in Freefall
The Kaduna Refining and Petrochemical Company represents perhaps the most heartbreaking case of industrial decline in Nigeria’s petroleum sector. Located in the northern commercial hub of Kaduna, the facility once served as a symbol of Nigeria’s industrial diversification beyond the oil-producing south.
The refinery’s decline has been particularly devastating because of its integrated role in the local economy. Unlike the southern facilities, which operate in regions with diverse economic activities, Kaduna’s refinery was a cornerstone of the local economy, supporting thousands of direct and indirect jobs.
The Human Cost
The impact on local communities provides the most compelling evidence of the refinery’s collapse. Paulina, a bar attendant in Kapam, a community that borders the refinery, captured the transformation: “This place used to be alive. You would see flames from the furnace, hear the noise of work going on. Now, nothing. They keep saying ‘maintenance’ but we have heard the same story for years with no end in sight.”
The economic devastation extends throughout the surrounding area. Musa, who operates a small kiosk near the refinery gates, described the dramatic change: “Back then, workers would come to our shops every day. Now, people hardly pass here. Even security men have been reduced. We survive on small things, not like before.”
Housing markets, transportation services, and retail businesses that once thrived on the refinery’s activity have withered. The ripple effects of the facility’s closure demonstrate how industrial policy failures translate into human suffering.
The $740.6 Million “Quick-Fix”
In February 2023, NNPCL signed a $740.6 million contract for what officials termed a “quick-fix” repair of the Kaduna facility. The terminology itself was revealing—after years of comprehensive rehabilitation efforts, authorities had scaled back ambitions to more modest “quick-fix” solutions.
Officials promised 60% production capacity by December 2024, a target that came and went without achievement. The continued failure to meet even these reduced expectations has intensified criticism of the entire rehabilitation program.
Technical Deterioration Accelerates
A former engineer at the facility, speaking on condition of anonymity to avoid potential retaliation, provided technical insight into the challenges facing any future rehabilitation attempts: “When you leave a refinery idle for too long, corrosion sets in. Even if turn-around maintenance is completed, more workers will be needed.”
The human resource challenge is particularly acute. The facility once employed over 1,200 workers across various technical specializations. Today, fewer than 100 remain, representing a catastrophic loss of institutional knowledge and technical expertise.
This brain drain compounds the technical challenges. Modern refinery operations require not just functioning equipment but also skilled operators who understand the complex interplay of chemical processes, safety protocols, and quality control measures. Rebuilding this human infrastructure may prove even more challenging than repairing physical equipment.
Community Desperation
The prolonged uncertainty has bred deep cynicism among local residents. John, a Kapam resident, used a religious metaphor to capture the community’s frustration: “This is like the coming of our Lord Jesus Christ, everybody is waiting, and it is not coming.”
Aisha Mohammed, another resident, expressed the modest hopes that remain: “Even if the refinery starts operation at 60 per cent, that will be good. Last time, they promised similar targets, we saw flames, then silence. We are tired of promises.”
A security guard at the facility’s main gate perhaps best summarized the situation: “They say ‘quick-fix,’ but the fix feels slow. Nothing much has improved: no jobs, no fuel, just bad roads and high prices.”
The EFCC Investigation: Following the Money
The scale of the rehabilitation failures has attracted the attention of Nigeria’s premier anti-corruption agency. In May 2025, the Economic and Financial Crimes Commission launched a comprehensive investigation into the alleged mismanagement of the $3 billion rehabilitation funds.
The investigation has targeted high-level NNPCL officials, including recently dismissed managing directors. The timing of these dismissals, coinciding with the investigation’s launch, suggests the seriousness with which authorities are treating the allegations.
The EFCC’s involvement represents more than just a response to public pressure. The agency’s investigations often uncover systematic patterns of corruption that extend beyond individual cases of misconduct. Early indications suggest the refinery rehabilitation program may have been compromised by the same governance failures that have plagued other major infrastructure projects in Nigeria.
The Broader Economic Impact
Import Dependency Deepens
The failure of the rehabilitation program has serious macroeconomic implications for Nigeria. The country’s continued dependence on imported petroleum products represents one of the largest drains on foreign exchange reserves, contributing to persistent currency pressures and inflation.
Current import costs for refined petroleum products exceed $10 billion annually—resources that could have been deployed for education, healthcare, infrastructure, or other development priorities. The failed refinery rehabilitation represents not just wasted investment but also foregone opportunities for economic transformation.
Regional Implications
Nigeria’s refining failures have broader West African implications. As the region’s largest economy and most significant oil producer, Nigeria was positioned to serve as a petroleum product hub for neighboring countries. The continued inoperability of domestic refineries means this regional leadership opportunity remains unrealized.
Countries like Ghana and Côte d’Ivoire have made significant investments in refining capacity, positioning themselves to capture market share that might otherwise have belonged to Nigeria. This represents a strategic loss beyond the immediate financial costs of the failed rehabilitation program.
Employment and Skills Erosion
The refinery failures have contributed to Nigeria’s broader deindustrialization challenges. The petroleum refining sector once provided high-quality employment for thousands of technical specialists, from chemical engineers to skilled technicians.
The prolonged shutdown of these facilities has led to a brain drain, with many experienced professionals emigrating or transitioning to other sectors. Rebuilding this technical capacity will require substantial time and investment, even if the physical infrastructure challenges are eventually resolved.
NNPCL’s Response and Future Plans
Despite mounting evidence of failure, NNPCL maintains an optimistic public posture regarding the refineries’ future. Spokesperson Andy Odeh provided a measured response to CoolNews inquiries: “The NNPC is determined to provide a sustainable solution to its three refineries in order to restore them into full operations. Detailed technical and commercial reviews of the Port Harcourt, Kaduna, and Warri refineries are ongoing.”
The mention of “detailed technical and commercial reviews” suggests recognition that previous rehabilitation efforts may have been inadequately planned or executed. However, the continued emphasis on restoration rather than alternative strategies raises questions about whether lessons have been learned from past failures.
Alternative Approaches and Global Comparisons
The Dangote Factor
The contrast between Nigeria’s state-owned refinery struggles and private sector success is stark. Aliko Dangote’s $19 billion refinery, located in Lagos, represents the world’s largest single-train petroleum refinery with a capacity of 650,000 barrels per day.
Built with private capital and management, the Dangote refinery achieved operational status while the government’s rehabilitation efforts stalled. This success highlights the potential for alternative ownership and management models in Nigeria’s petroleum sector.
International Best Practices
Successful refinery rehabilitation programs in other countries typically involve comprehensive technical assessments, realistic timelines, professional project management, and clear accountability mechanisms. The Nigerian approach appears to have lacked several of these elements.
Countries like Saudi Arabia, India, and Singapore have successfully modernized and expanded refining capacity through disciplined project management and substantial technical expertise. Nigeria’s failures suggest fundamental gaps in project planning and execution capabilities.
The Path Forward: Lessons and Recommendations
Immediate Actions Required
The current situation demands immediate and decisive action to prevent further deterioration of the facilities and loss of public resources. Key priorities include:
Comprehensive Technical Audits: Independent technical assessments of all three facilities to determine actual rehabilitation requirements and costs.
Financial Accountability: Complete investigation and prosecution of officials responsible for fund mismanagement, with recovery of stolen or misdirected resources.
Policy Clarity: Clear decisions about the future of each facility, including potential partnerships with private operators or outright privatization.
Community Engagement: Honest communication with affected communities about realistic timelines and expectations.
Strategic Alternatives
The repeated failures suggest that traditional rehabilitation approaches may be inadequate for the scale of challenges facing Nigeria’s refining sector. Alternative strategies worth considering include:
Public-Private Partnerships: Joint ventures with experienced international refinery operators who can provide technical expertise and management capabilities.
Phased Privatization: Gradual transfer of facilities to private operators with proven track records in refinery management.
Regional Cooperation: Partnerships with other African countries to develop shared refining capacity and expertise.
Technology Leapfrogging: Investment in smaller, modular refinery technologies that may be more appropriate for Nigeria’s technical capabilities and market conditions.
Long-term Institutional Reforms
The refinery failures reflect broader governance challenges that extend beyond the petroleum sector. Addressing these requires comprehensive reforms including:
Professional Project Management: Development of specialized project management capabilities within government agencies.
Technical Capacity Building: Long-term investment in technical education and training programs.
Transparency and Accountability: Stronger oversight mechanisms for major infrastructure projects.
Realistic Planning: More conservative and realistic approaches to project timelines and cost estimates.
Conclusion: A $3 Billion Lesson in Governance Failure
The ghost refineries of Port Harcourt, Warri, and Kaduna stand as monuments to one of Nigeria’s most expensive governance failures. The $3 billion rehabilitation program, designed to transform Africa’s largest oil producer into a refining powerhouse, has instead become a case study in systematic mismanagement, corruption, and the gap between political promises and technical reality.
The human cost of these failures extends far beyond financial losses. Communities that once thrived around active refineries now struggle with unemployment and economic decline. Workers collect salaries for jobs that no longer exist while Nigeria continues to spend billions importing products it should be producing domestically.
Perhaps most troubling is the pattern of denial and obfuscation that has characterized official responses to clear evidence of failure. The gap between public statements and operational reality suggests an institutional culture that prioritizes public relations over problem-solving.
Yet the story of Nigeria’s ghost refineries also offers opportunities for learning and reform. The failures have created space for private sector success, as demonstrated by the Dangote refinery. They have exposed governance weaknesses that extend beyond the petroleum sector. And they have generated public awareness and accountability pressure that may help prevent similar failures in the future.
The choice facing Nigeria is clear: continue pouring resources into failed approaches or embrace the fundamental reforms necessary to build a functional refining sector. The ghost refineries can serve as either monuments to failure or foundations for a more transparent, accountable, and effective approach to industrial development.
The workers who show up each day to facilities that produce nothing, the communities that wait for promised prosperity that never arrives, and the nation that continues to import what it should produce domestically all deserve better than the status quo.
Whether Nigeria can deliver that better future will depend on its willingness to confront uncomfortable truths about governance, accountability, and the gap between political ambition and administrative competence. The ghost refineries stand ready to serve either as monuments to failure or as the foundation for genuine reform.
The choice remains to be made.
This investigation was conducted over six months and involved visits to all three refinery locations, interviews with over 50 sources including current and former workers, community members, industry experts, and government officials. CoolNews will continue to monitor developments in this ongoing story and the related EFCC investigation.
For tips, feedback, or additional information related to this story, contact our investigation team at coolnewsc@gmail.com